8/18/03-8/22/03 Restoration of NG1 and additions to AND/R
![]()
Ladder racks, motor cables, and detector cables are installed in the trench on top of the electrical power and air lines.
![]()
The control station for the NG1 reflectometer was set up in its new location...
and
![]()
![]()
... the cables were re-routed to the front, through new ladder racks, to the electronics racks.
![]()
"No Entry" signs are mounted above the neutron beam paths for both NG1 and AND/R and the AND/R shutter control switch is mounted to the beam stop (not shown).
![]()
The NG1 shutter control / safety system is re-wired for it's new configuration
![]()
Slit #1 is installed just downstream of the monochromator inside the shielding.