2014-2015 Operations Schedule

This schedule is a best estimate of cycle dates through September 13, 2015. It should be noted that startup and shutdown dates can be altered by elements not under the control of Operations, such as storms or unexpected maintenance. As much as possible, Operations will hold to a schedule of approximately 38 days of operation, then a shutdown of 15-20 days duration. Please note the extended shutdown beginning in February for 5 weeks.

2014
OCTOBER 18 - NOVEMBER 11 SHUTDOWN
NOVEMBER 12 - DECEMBER 21 OPERATING
DECEMBER 22 - JANUARY 4 SHUTDOWN
2015
JANUARY 5 - FEBRUARY 13 OPERATING
FEBRUARY 14 - MARCH 24 SHUTDOWN
MARCH 25 – APRIL 17 OPERATING
APRIL 18 – APRIL 19 SHUTDOWN
APRIL 20 – MAY 6 OPERATING
MAY 7 – MAY 25 SHUTDOWN
MAY 26 – JULY 5 OPERATING
JULY 6 – JULY 19 SHUTDOWN
JULY 20 – AUGUST 28 OPERATING
AUGUST 29 – SEPTEMBER 13 SHUTDOWN
  
  